Storm outage prediction: from a weather forecast to staged crews
How a storm outage prediction model turns a weather forecast into district damage estimates and a crew staging plan, up to five days before the storm.
By Dr. Aous Abdo21 November 2026
A utility usually knows a storm is coming days before it arrives. The weather forecast says where it’s tracking and how strong it should be. What the forecast doesn’t say is which districts will lose power, how much equipment will be damaged, and where crews, poles, transformers and wire need to be before the first pole comes down.
That gap is what a storm outage prediction model is for. This guide covers what the model has to answer, how we built one for Southern California Edison, the data it ran on, and how its output becomes a staging plan.
The operational problem: knowing where to stage crews
Storm response at a large utility is a staging problem. Crews and materials have to be in roughly the right place before the weather arrives, because moving them afterward is what turns a six-hour outage into a two-day one.
A weather forecast alone doesn’t support that decision. It describes the storm, not the grid’s exposure to it. The utility we worked with had weather forecasts and it had asset records, but nothing connecting the two: no way to turn “a storm is coming” into “these districts will take damage, of roughly this magnitude, needing roughly these resources.”
Across the United States, most of the difference from one year to the next in how long customers go without power comes from major events such as hurricanes and other storms, according to the U.S. Energy Information Administration.
Hours without power per U.S. customer, 2015–2025
What an outage prediction model has to answer
For the people staging crews, a useful model answers four questions, in this order:
- Where will damage occur? Which districts in the service territory are likely to take damage from this storm.
- How badly? Within those districts, which grid assets are likely to be damaged.
- What will it take to restore? The crews, materials and hours the predicted damage will need.
- How far ahead? Early enough to move crews and materials before the storm, not after the outages start.
The first two are forecasts of damage. The third turns damage into resources, and it’s the one the operations team acts on. The fourth decides whether any of it is useful: a damage forecast that arrives after crews can no longer be moved doesn’t change the response.
Each answer is an estimate. A planner deciding how many crews to send to a district needs to know how far the number could reasonably be off, which is why a damage forecast should carry its uncertainty rather than a single figure.
Why the model is built in two stages
The model we built for Southern California Edison splits the damage forecast into two stages, so each stage answers one question.
- Stage one: will it break? Predicts the likelihood of damage occurring in a given district.
- Stage two: how badly? Predicts damage to specific grid assets within the districts stage one flags.
A third component, the resource model, converts the predicted damage into the crews, materials and hours required.
The split matches the questions above. “Is this district at risk?” is asked of the whole service territory. “Which poles and transformers in it?” only needs asking where the answer to the first question is yes, so stage two runs inside the flagged districts rather than across every asset the utility owns.
The two-stage storm damage model
Flagging a district means its score has crossed a threshold, and where that line sits is an operational decision as much as a modeling one. Set it low and more districts get flagged, so crews are staged for damage that doesn’t come. Set it high and fewer false alarms reach the planners, at the cost of districts that take damage without crews nearby. That’s the trade-off precision and recall describe, and the right balance depends on what a missed district costs the utility compared with an idle crew.
The data an outage prediction model uses
The Southern California Edison model drew on three kinds of data.
- Weather. Feeds from multiple open sources, ingested and prepared automatically.
- Grid assets. Static data on the number, age and location of poles, transformers and other equipment exposed to a given storm track.
- Tree cover and soil moisture. The geospatial layer that turned out to matter most, because trees and debris striking lines cause most storm damage.
Turning a damage forecast into crew staging
A district-level damage map is not yet a staging plan. The resource model is the step that makes it one: it takes the predicted damage and converts it into the crews, materials and hours needed to restore each district.
The output then has to reach the people making the call. For Southern California Edison that took two forms:
- A cloud-hosted dashboard with interactive maps showing predicted damage by district, the resources required, and the hours to restore.
- Automated severe-weather alerts by email, so the model reaches people who aren’t sitting in front of a dashboard at 4am.
The forecast horizon was up to five days. Five days is roughly how long it takes to move crews, which is why the horizon matters as much as the accuracy of the damage model.
From weather forecast to staged crews
Building the dashboards, feeds and alerts that put model output in front of an operations team is our decision-support platforms work. The models behind them are our AI and data science delivery work, and when a model needs an operator interface, the two are scoped together.
What we delivered for Southern California Edison
Over two years, on a subcontract, we built Southern California Edison a storm damage platform: the two-stage damage model, the resource model, the automated weather feeds, the dashboard and the email alerts described above.
- forecast horizon
- 5 daysforecast horizon
- model stages
- 2model stages
- engagement
- 2 yearsengagement
- reduction in outage times, client-reported
- 15%reduction in outage times, client-reported
The client reported outage times falling by 15%, with damage predicted up to five days ahead, enough lead time to stage crews and materials before the storm arrives. The full case study is Predicting where a storm will break the grid.
The same kind of event looks different from the federal side. For the Cybersecurity and Infrastructure Security Agency, as a subcontractor, we forecast how a hurricane moves through dependent critical infrastructure, from a port to a refinery to the region it supplies. That work is described in Predicting how a hurricane cascades through US critical infrastructure.
What a utility needs in place to start
The inputs to the Southern California Edison model point to what a utility needs to have before a project like this starts.
- Asset records with locations. The number, age and location of poles, transformers and other exposed equipment. This is the part only the utility holds.
- Tree cover and soil moisture data for the service territory.
- Weather forecasts. The Southern California Edison model took its weather from multiple open sources.
- A defined staging decision. Who decides where crews and materials go, how far ahead, and what they need to see to decide. The resource model is built around that decision, and the dashboard and alerts are built around the people who make it.
Whether the records a utility holds are complete enough to support a model is the first thing to check, before anything is built.
Questions about storm outage prediction
How far ahead can storm damage be predicted?
The model we built for Southern California Edison predicted damage up to five days ahead. Five days is roughly how long it takes to move crews, so that horizon leaves time to stage them before the storm arrives.
Does the model score every asset the utility owns?
No. Stage one scores every district for the likelihood of damage, and stage two predicts asset-level damage only inside the districts stage one flags.
Why does tree cover matter so much?
Because trees and debris striking lines cause most storm damage. That’s why tree cover and soil moisture sit alongside weather and asset data as inputs.
How does a damage forecast become a staging plan?
Through the resource model, which converts predicted damage into the crews, materials and hours each district will need. The results reach the operations team through a dashboard and email alerts.
Start with the decision
Tell us what you're trying to predict — storm damage, equipment failure, which employees are likely to leave. We'll look at the data you already have and tell you whether it can support the decision, before you've committed to anything.